As per approved drawings, Demarcation of plots was done by Total Station Machine
(i) RCC Cum brick wall having thickness of 230 mm. (ii) Height of the boundary wall will be 6 feet from 0-0 level.
Two 9 m Roads having length of 70 m each and one 7.5 m road having length of 75 m will be constructed. The road will be constructed in several steps- (i) 3 times backfilling of soil. (ii) After each step of soil feeling, compaction and curing will be done. (iii) 2 times GSB layering having thickness of 150 mm each one 6 m of width on 9 m road and 4.5 m of width on 7.5 m of road, then compaction and curing will be done. (iv) WBM Bituminous layer of thickness 150 mm.
On the remaining 3 m compacted soil (1.5m on each side), we will lay interlocking tiles on the footpath.
For every individual Villa, drinking water connection through 90 degree dia PVC line.
Sewer System will be constructed in following steps- (i) Excavation as per level of sewer in approved drawings (ii) PCC. (iii) NP3 pipes having 300 degree dia of slope in ration of 1/200 will be used in the sewer system. (iv) Backfilling of soil and plaster. (v) Waste water will discharge into sewer pipes, then sewer water will discharge into STP.
(i) Excavation as per level of draining line in approved drawings. (ii) PCC (iii) NP3 pipes having 300 degree dia of slope in ratio of 1/200 will be used in the drainage system. (iv) Backfilling of soil and plaster (v) Drainage water will be discharged into the RWH pit by NP3 pipes.
(i) 10 percentage of the total plot area which is 678.15 sq.m (ii) The level of the green area will be 75 mm down from road level.
(i) 35 trees will be plated in the green area. (ii) Different types of trees and flowers will be planted.
(i) 25 KVA transformer will be placed. (ii) 3 m distance between two street lights. (iii) 9 feet height 0-0 level.
(i) Sector shopping provided having an area of 181.09 sq.m. (ii) Convenient shops provided having an area of 157.07 sq.m. (iii) Club house having an area of 73 sq.m.
STP of 70 KLD will be provided having an area of 70 sq.m.
Garbage area provided having an area of 33.19 sq. m.
RWH (Rain water harvesting) having an area of 10 sq.m. will be provided (i) 250mm 230mm dia bore filled with pea gravels. (ii) 160 degree PVC slotted pipe. (iii) 50-150 mm size boulders (iv) Mesh (v) Gravel 5-10 mm (vi) Coarse sand (1.5 to 2 mm) (vii) Geotextile (160 GSM) (viii) 600 x 600 x 100 mm RCC Deflector or stone slab
(i) Electrical panel room and 100 percent power backup. (ii) Two 125 KVA D.G will be provided.
(i) Ring line having 150mm thickness. (ii) Extinguisher in each villa (iii) Fire tank of RCC. (Capacity as per drawings)
(i) Gym (ii) Swimming pool (iii) Banquet hall
(i) Fire Alarm system in panel room. (ii) NT smokers in all villas
As per requirement
Total Area
9070.00 m²
97628.57 ft²