NewActive

THE BROOK PHASE-2

Gautam Buddha Nagar, Uttar Pradesh
20-05-2024
Launch Date
New
Type
13-05-2029
Completion Date

Overview

Launch Date

Invalid Date

Completion Date

13-05-2029

RERA ID

UPRERAPRJ535539/09/2024

Basic Details

Project TypeNew
Project CategoryResidential
Total area in round figure (Sq.mt.)8000
Project NameTHE BROOK PHASE-2
Registration Fee (in Rs.)45000
AddressPLOT NO.:- GH-03C
Village/Locality/Sector etc.SECTOR -12
StateUttar Pradesh
Project Duration (In month)60
DistrictGautam Buddha Nagar
Original Start Date-
TehsilDadri
Proposed Start Date20-05-2024
Sanctioning Competent AuthorityGreater Noida Authority
Project Cost (in Lacs)27415
Proposed Completion Date13-05-2029

Location

Latitude

28.56118

Longitude

77.48200

Bank Details

Account Details
Name of the AccountBLESSINGS HOMZ PVT LTD COLLECTION ACCOUNT FOR THE BROOK PHASE-2
Account Number414605001942
Bank NameICIC Bank
Branch NameCHERRY COUNTY
Branch AddressSHOP NO9A-9B GH-05B TECHZONE-4 GEATER NOIDA WEST
IFSC CodeICIC0004146
Branch DistrictGautam Buddha Nagar
Branch StateUttar Pradesh
Branch Email Addresschaudhary.ankush@icici.com
Separate Account Details
Name of the AccountBLESSINGS HOMZ PVT LTD SEPRATE B ANK ACCOUNT FOR THE PHASE -2
Account Number414605001941
Bank NameICICI BANK
Branch NameCHERRY COUNTY
Branch AddressSHOP NO. 9A-9B GH-05B TECHZONE -4 GREATER NOIDA WEST
Branch StateUttar Pradesh
Branch DistrictGautam Buddha Nagar
IFSC CodeICIC0004146
Transaction Account Details
Name of the AccountBLESSINGS HOMZ PVT LTD TRANSACTION ACCOUNT FOR THE BROOK PHASE -2
Account Number414605001940
Bank NameICICI BANK
Branch NameCHERRY COUNTY
Branch AddressSHOP NO. 9A-9B GH-05B TECHZONE-4 GREATER NOIDA WEST
Branch StateUttar Pradesh
Branch DistrictGautam Buddha Nagar
IFSC CodeICIC0004146

Development Works

Demarcation of Plots

The project is demarkated with two roads each of 24 meter running along the south west side and north west side .The plot measures 117.84m in length and 173.38m in breadth . Geographical coordinates of the centre of the project site are 28.33.39.72 N and 77.28.57.22 E. Elevation of the project site is 211m aboe sea level. Project site is well connected with the Greater Noida West Link Road . Nearest railway station is Maripet Station at a distance of 3.8 km from site.

Boundary Wall

The boundary wall will consist of brick work up to a height of 5ft and with iron grill on top. A storm water drain is running along the boundary wall on 02 sides. The other 02 sides of the boundary wallhave adjoining projects on plot No. GH-04B GH-03B

Road Work

The project will consist of 8 meter internal wide road to facilitate vehicle and pedestrian movement. The CC roads are complete with VDF flooring which are maintenance free and have longer life spans. The roads in front of lobbies will be finished with pavers laid in design as per architecht . The road on ground floor is bounded by kerb stone and saucer drain towards the boundary wall.

Footpaths

The project will have footpath for pedestrian running along the towers. The footpaths are finished with pavers and or granite stones. The footpaths are illuminated with decorative lights placed at appropriate distance.

Water Supply Including Drinking Water Facilities

The drinking water will be supplied by GNIDA. Service connection amount has been paid as part of sanctioning of drawings. The drinking water system includes 02 raw water tanks summing upto 230 KL raw water received from GNIDA. This raw water after filtration is stored in 02 drinking water tanks of total capacity of 230 kl This drinking water is pumped by hydro pneumatic pumpsto overhead tanks on terrace of each tower.

Sewer System

The project will have own STP installed in premises . 340 KLD stp in 2 phase is proposed and sanctioned. Sever watertreatment includes primary treatment through Bar Screen and Equilisation tanks. Thereafter secondary treatment includes MBBR reactors. Teriary treatment includes multigrade filetr and activated carbon filters. Thereafter the treated water is stored in 02 treated water tanks in STP pump housetotaling 230 kl. The treated water is used in flushing usage and horticulture activities.

Drain

Sewer water is treated in an onsite STP plant. The treated water frm STP is proposed to be used in horticulture and flusing activities. The rain water is harvested through a netwrk of 10water harvesting pitseach with a capacity of 28.49 cum water. Storm water drains for internal roads is discharged into storm water drains running beside boundary wall.

Parks

The project will be having a central park having a fragrance garden and decorative plants. The project is providing 5000 sqm landscaped area on podium. The planned facilities are Jogging Track, swimming pool, celeberation lawns, pavilions and plaza for sitting, kids play area and gardens., outdoor gymnasium, yoga meditation lawn, amphitheatre, multipurpose court to name a few.

Tree Planting

The project will be having trees to comply with the norms of GNIDA. 154 trees are proposed at site towards landscaping. The varietes of trees are 39 Ashoka trees, 38 Gulmohar trees, 39 Botte palms, and 38 bamoo trees. Beside the trees 7703 landscaped green plants will be provided on ground and stilt floor.

Design For Electric Supply Including Street Lighting

The company draw its electricity from grid provided by UPPCL or NPCL. The proposed electrical load is 1857 KW for apartments 507 KW load for common services and 420 KW for EV charging setup. the proposed load will be drawn from NPCL/UPPCL distribution and will be handled by stepdown transformers . The DG bacup is provided by 02 650 KVA DG sets.

Community Buildings

The community building are as per sanctioned drawings and are planned on 1444 sqm area. The facilities planned in communty building includes changing rooms and toilet for swimming pool, party hall complete with toilet and kitchen, gymnasium. Billiards and TT room, card room and Indoor games area, 02 guest rooms, kids play area, steam room and sauna room, kitchen and toilet at terrace.

Treatment and Disposal System of Sewage and Sullage water

340KLD STP is proposed and sactioned. . Sever water treatment includes primary treatment through Bar screen and equilisation tanks. Thereafter secondary treatment includes MBBR reactors, Tertiary treatment includes mutigrade filterand activated carbon filters. Therafter the treated water is stored in o2 water tanks in STP pump house totalling 230 KLD. This treated watre is used for flushing and horticulture activites.

Solid Waste Management And Disposal System

A plant room fr OWC machine measuring 50 sqm , part of solid waste management is sanctioned in submission drawings. Door to door collection system is proposed for collection of domestic waste. the bio degrable waste will be treated in organic waste convertor. the residue from OWC will be used as manure. Recyclable waste will be sold to GNIDA authorised vendors.

Water Conservation System

The project has been precertified as gold rating under IGBC. Accordingly, project has been proposed to use low flow plumbing fixtures that saves a signifiant amount of water along with usage of pressure reducing valves in water riser.

Energy Management System Including Use of Renewable Energy

It is proposed to use solar renewable energy to cater to Common area lighting or 1 OF DEMAND LOAD. All common area and exteroior lights will be LED based. It is proposed to use pumps with mimimum efficiency of 70 percent and motors with efficiency over 85 percent.

Fire Protection And Fire Safety System

Fire fighting pump rooms and fire fihting tanks have been provided for fire protection system. 2 No.s fire tank of capacity 250 kl provided. fire protection includes Main Fire Pumps, Jockey pumps, DG fire pumps, Yard Hydrants, FHC at each floor, sprinklers in each dwelling area, refuge area at 19th floor of each tower. Additionally 10000 L capacity is provided for fire fighting at OH tank in every tower.

Social Infrastructure And Other Public Amenities Including Public Health Services

The project will be having club with gymnasium and swimming pool.

Emergency Evacuation Services

As a statutory requirement from fire services, refuge area is provided on 1th floor of each tower. Each tower is provided with 02 staircases for evacuation. The width of these staircase are 1500mm and 2000mm.

Other Miscellaneous Work

we have proposed EV charging setup, Green certified glass for building, proper vantilation and PV setup to harness slar lights. A provision has been provided for mechanical parking by providing adequate light in basement to cater to future needs of parking.

Documents

Lease Deed

No: 10900/16 | Date: 29-04-2016

Details of Encumbrances

Other Plan(If Any)

Proforma of Completion Certificate(Occupancy)

Proforma of Completion Certificate(Occupancy)

CA CERTIFICATE

CA CERTIFICATE

Details of Encumbrances

Uploaded: 28-05-2024

Commencement Certificate

Uploaded: 28-05-2024

Other Plan(If Any)

Uploaded: 04-09-2024

Proforma of Application Form

Uploaded: 28-05-2024

Proforma of Allotment Letter

Uploaded: 28-05-2024

Proforma of Conveyance Deed

Uploaded: 28-05-2024

Waste Disposal Plan

Uploaded: 12-09-2024

Water Supply Plan

Uploaded: 12-09-2024

Electricity Supply Plan

Uploaded: 12-09-2024

Development Work Plan

Uploaded: 14-08-2024

Affidavit

Uploaded: 28-06-2024

CA CERTIFICATE

Uploaded: 26-08-2024

ARCHITECT CERTIFICATE

Uploaded: 12-08-2024

ENGINEERS CERTIFICATE

Uploaded: 12-08-2024

Other

Uploaded: 17-09-2024

Proforma of Agreement for Sale

Uploaded: 28-05-2024

Permits

Orignal Permit NoPLG/BP SM-06-Dec-2023 19817
Orignal Permit Date14-05-2024
Valid Upto13-05-2029
Revalidated Permit No-
Revalidated Permit Date-
Revalidated Permit Valid Upto-
Permit Extendable Upto13-05-2029
End Date13-05-2029
Uploaded Approve LayoutOpen
Uploaded Sanctioned LetterOpen
Uploaded Approved MapOpen
Uploaded Floor Plan Of All TypesOpen
Uploaded Project SpecificationsOpen
Uploaded Sajra DetailOpen

Project Team

Contractor Name (if any)KAMAL AND ASSOCIATES PVT LTD
Contractor AddressPLOT NO.-01 THIRD FLOOR LSC MAYUR VIHAR PHASE -2 DELHI 110091
Architect NameDESIGN FORUM INTERNATIONAL PVT LTD
Architect AddressK-47 KAILASH COLONY DELHI-110048
Architect Licence NumberCA/95/18738
Structural Engineer NameKEEN ASSOCIATES PVT LTD
Structural Engineer AddressH-53 FIRST FLOOR SECTOR-63 NOIDA 201301
Mobile number(Project Co-ordinator)9818608010

Land Details

AFS

Showing 3 blocks with 441 units

Property Summary

Total Carpet Area

34143.20 m²

367513.99 ft²

Total Units

429

1 different types

Blocks & Floors

3

31 floors across all blocks

Parking

0

0 garages, 0 open

Average unit size:79.59 m²
Balconies:428
Parking ratio:0.00 per unit

Block E

165 units

Block F

165 units

Block G

111 units

Khasra Details

Total Area

20000.00 m²

215278.00 ft²

1 plot
Plot
TypePlot
Khasra/Plot NoGH-03C
Area(In Sq. Mt.)20000

Other Details

Contractor Name (if any)KAMAL AND ASSOCIATES PVT LTD
Contractor AddressPLOT NO.-01 THIRD FLOOR LSC MAYUR VIHAR PHASE -2 DELHI 110091
Architect NameDESIGN FORUM INTERNATIONAL PVT LTD
Architect AddressK-47 KAILASH COLONY DELHI-110048
Architect Licence NumberCA/95/18738
Structural Engineer NameKEEN ASSOCIATES PVT LTD
Structural Engineer AddressH-53 FIRST FLOOR SECTOR-63 NOIDA 201301
Mobile number(Project Co-ordinator)9818608010