PROJECT COMPLETED- All the plots are demarcated as per the sanction plan by Agra Development Authority to the exact dimension and direction.
PROJECT COMPLETED- 5 feet high brick wall constructed in cement mortar, plastered and painted with foundation 4 feet deep to keep strong anchor is constructed. This project is access controlled with single gate entry-exit.
PROJECT COMPLETED- A cement concrete road is constructed as per the approved map and design to cater for the domestic loads. The sub base and base are compacted and a 200mm CC layer with antiskid properties are laid for safe and smooth ride.
PROJECT COMPLETED- NotApplicable
PROJECT COMPLETED- The ground water supply of potable water pumped by a submersible pump to the Over head tank is supplied to the individual units through PVC pipe lines leading to all plots.
PROJECT COMPLETED- 150 mm dia hume pipes are lain to the desired slopes for smooth flow. The man hole of 0.6m dia are located at all critical location . The sewer line is connected o the STP.
PROJEC TCOMPLETED- Lined drains are designed and constructed to cater for the domestic drains and surface runoffs. The depth and slopes are maintained to ensure quick removal.
PROJECT COMPLETED- Lush green park , with play area or kids and sitting area for elders as per the sanction map by Agra Development Authority.
PROJECT COMPLETED- Trees of different type suitable to the soil type are planted along the boundary wall, periphery of park and suitable locations.
PROJECT COMPLETED- A dedicated transformer, designed number of electric poles and distribution boxes are installed as per the sanction by electrical department to cater for the domestic use of electricity of residents in future
Not Applicable
PROJECT COMPLETED- A state of art sewage treatment plant is designed and constructed to cater for the sewage domestic waste from the future residents of the colony. The treatment will bring the sewage within the permissible limits before disposal.
PROJECT COMPLETED- A dalab-ghar along with dustbins are constructed and installed respectively for the smooth collection and disposal of domestic waste
PROJECT COMPLETED- Rain water harvesting pits are installed with filtration system to collect the surface runoff and allow the water to percolate to help sustain the water table. The minimum depth of 7 m is kept.
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Showing 1 blocks with 4 units
Total Carpet Area
0.00 m²
0.00 ft²
Total Units
0
1 different types
Blocks & Floors
1
1 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
13527.01 m²