Launch Date
Completion Date
RERA ID
29.437556
77.71297
DEMARCATION OF PLOTS WILL BE DONE BY TOTAL STATION AND WE WILL MAKE BRICK MARKING AT EACH CORNER OF PLOT
BRICK WORK OF 9 INCH THICKNESS HAVING HEIGHT OF 6 FEET WILL BE CONSTRUCTED HAVING THE RCC PILLERS AT A DISTANCE OF 10 FEET
RCC ROAD HAVING THE THICKNESS OF 8 INCH WILL STEEL MACHING OF 10MM DIAMETER WILL BE CONSTRUCTED.
INTERLOCK TILES OF 35MM THICKNESS WILL BE USED TO COVER UP THE FOOTPATH AREA.
WATER LINES HAVING THE DIAMETER OF 5 INCH AND 6 INCH WILL BE LAID AND CONNECTED WITH THE OVER HEAD TANK OF 2.5LAKH LETER CAPACITY.
THE SEWERVAGE LINE HAVING THE DIAMETER OF 8INCH TO 24 INCH WILL BE LAID DOWN AND WILL CONNECTED TO THE SEWARAGE TREATMENT PLANT.
THE DRAIN LINES HAVING THE THICKNESS OF 6 INCH AND 8 INCH WILL BE LAID DOWN WHICH WILL BE CONNECTED TO THE RAIN WATER HARVESTING SYSTEM.
THE PROPER HORTICULTURE WORK WILL BE DONE.125 tree PER HECTARE WILL BE PLANT,
ROAD SIDE TREES AND 2 TRESS IN FRONT OF EACH PLOT WILL BE PLANTING.125 TREE PER HECTARE WILL BE PLANT
MS POLE WILL BE INSTALL AS PER DESIGN AND TWO TRANSFORMER WILL BE INSTALLED.
NA
SEVRAGE TRETMENT PLANT WILL BE INSTALLED HAVING A CAPACITY OF 3 LAC LITRE PER DAY DISCHARGE
NA
3 RAIN WATER HARVESTING PITS WILL BE CONSTRUCTED.
NA
4 FIRE WALLS WILL BE INSTALLED.
NA
NA
NA
Showing 1 blocks with 2 units
Total Carpet Area
0.00 m²
0.00 ft²
Total Units
0
1 different types
Blocks & Floors
1
1 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
23470.00 m²
252628.73 ft²