25.221414
83.013621
Plot line demarcarted
2.1m. Heigh boundary wall composed of 230mm thick brickwork and RCC columns @ 4.0m. C/c along with plinth beam. The wall to be finished with plaster & paint.
6m. wide concrete road
1.5m. Wide footpath with interlocking pavers along driveway & in green areas as/landscape design.
Source of water would be city mains/ tanker water and bore well water after seeking necessary approvals for same. Water will be first stored in UG tanks from where is pumped to Overhead tanks and fed to individual units thru gravity system.
Sewage to be collected thru drains & will disposed in municipal sevar line.
Proper drainage system planned for both sewage & storm. Storm water is connected to rain water harvesting pits. All drainage below gravity lvl. Would be connected & drained into a sump & then pumped into the storm drain.
Adequate open breathing space in the form of parks & green areas to be provided as/local byelaws. Parks are equipped with all facilities like jogging track, seating space, kids play area, etc.
Adequate no. Of plantation in the form of trees, shrubs, plants will be provided in green open spaces .
We have design the system as per local electricity board and consider centralized Transformer , panel Feeder pillar and DG back for common service like external lighting , pump room etc.
It comprises of facilities of Hall, Yoga & Mediation room, Indoor games and Gym. It also has guest rooms for visitors.
Centalized sewerage system shall be provided . All sewerage water should be collected through drain & will connect with the municiple sewerage system.
As per requirement.
Proper sanitary fixtures with ISI mark and rated for water saving to be used. Rain water harvesting pits to be used for ground water recharge.
We will use LED lights fitting in external area & all the equipment shall have energy efficient motor.
Underground RCC water storage tanks has been created within the Complex (common for all building). A pump house adjacent to the fire storage tank where various fire water pumps and associated equipment would be located & overhead tank shall be provided at terrace. All arrangements as per NBC shall be provided.
"Following social infrastructure and public amenities will be provided: ? Power Back-up in common areas. ? round-the-clock security features, including CCTV surveillance systems, firefighting equipment and intercom facility ? Health Club "
Fire evacuation plans to be installed in common areas
Not applicable.
Showing 1 blocks with 121 units
Total Carpet Area
18529.46 m²
199449.25 ft²
Total Units
195
4 different types
Blocks & Floors
1
17 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
16718.00 m²
179950.88 ft²