Launch Date
Completion Date
RERA ID
27.479043
27.480557
Demarcation of plot line with prefabricated RCC muddy on all four corner of plots
230mm wall in brick massonary with FPS bricks of class designation 75 in ratio of 1;6 cement mortar on RCC footing and colum structure
Providing and laying of bitumin over well compacted subgrade with GSB layers
Laying of Interlocking pavers of 40 mm over well compacted subgrade with GSB layers.
Laying of 160(OD) fresh water supply (UPVC 6 kg/Cm2 pipe), 125 (OD) fresh water supply (UPVC 6Kg./Cm2 pipe), 90 (OD) fresh water supply (UPVC 6Kg/Cm2 pipe), 63 (OD) Fresh water supply (UPVC 6KG/Cm2 pipe) with proper air valve, Sluice Valve in chamber, Scour Valve and fire Bridge outlet connection.
Laying of SN-4 Pipes DWC pipes and making of circular manholes and rectangular manhole (900-800 MM) with 600-600 mm manhole cover for main line with proper finished formation level, invert level of Manhole and connection level.
Laying of DWC / RCC pipes and making of Circular manhole, Storm Water SN-4 RCC NP-3 Pipe, Rectangular Catch Basin (700-700) for main line, Recatngular Catch basin (450-450-450) for plots (in plot owner schope), DE-Silting chamber size 4-2 M recharge well size 1.2 dia (EFF) with proper finished formation level, Invert Level of Manhole and connection Level.
Dressing and plantaion of parks with grass and trees.
Plantation of Various type of trees as per Landscape consultant drawings.
Laying of Overhead HT and LT Cables, Erection of poles with provision of required capacity transformers as per UPPCL guidelines with following Specification- Fixing of 30 W and 50 W LED Street Light fixtures ,9M steel Tubular Pole for supporting overhead line with connector Box (For LT line), 11M steel tubular pole for supporting overhead line with connector box (for HT line ), 2 Pole structure Steel Tubular for Supporting overhead line, 150/200 MM dia hume pipe for IT cable and 690 mm wide 750 mm depth trench for HT and LT cable.
Club house
Construction of STP collection tank along with modular treatment system, laying of DWC pipes from STP to homes as per MEP drawings.
Construction of Garbage Rooms in brick load bearing strucuture.
Making of Rain water harvesting pits as per approved plan on MAP and laying of Flushing and irrigation water supply line as per MEP drawings.
NA
NA
NA
NA
NA
Showing 1 blocks with 4 units
Total Carpet Area
0.00 m²
0.00 ft²
Total Units
0
1 different types
Blocks & Floors
1
1 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
50073.00 m²
538980.76 ft²