Launch Date
Completion Date
RERA ID
26.910329
80.938517
Plot demarcated via boundary wall
10 Feet High boundary wall is proposed along with the plot perimeter
6 Meter wide road is proposed in the building setback
Designated entry for pedestrian via footpath has been proposed
Source of water supply 1. Primary Source - Municipal Source 2. Secondary source- Borewell 3. Tertiary source- Tanker Intake provision for worst case
1. The soil waste generated from each water closet, urinal etc. is carried out through separate soil vertical stack into inspection chamber / sewer Manhole. a. Grease Separation Grease generated from the kitchen shall be separated and disposal off via prefabricated HDPE/SS grease separator unit with or without grinder arrangement. b. Sewage Treatment Plant - Based on MBBR / SBR technology of capacity 50 KLD
Drainage - Vented Dual Pipe System
Minimum 15 percent open area as green park has been proposed
Evergreen plants will be planted in the planned green areas
11KVHT single point connection is proposed.
Not Applicable
Sullage - The waste generated from floor traps, shower, kitchen, wash basins etc. is carried through separate waste stack into the gully trap. The gully trap shall discharge the waste into the sewer manhole. Sewage and Sullage disposal - The sewage and sullage is discharged into the main sewerage line which is routed towards the sewage treatment plant.
For solid waste management municipal approved waste service provider will be deployed
Flushing water supply - cater for the flushing demands. TSE shall be used. Gravity Feed supply. Horticulture water supply - TSE (Treated Sewage Effluent) will be used to cater for the horticulture demands.
Energy Management System is proposed which provides flexibility of monitoring energy from all electrical feeders and key energy performance parameters on hourly / daily basis through notifications. On grid solar PV system of 100 kW is proposed considering 5 percent sanction load
Fire Extinguishers, Internal/External Hydrants, Wet Riser System, Automatic Sprinkler System, Compartmentation - Physical, water based and retractable curtain, Wet chemical system, Gas Suppression system, Gas leak detection system
Not Applicable
a. An Addressable fire alarm system with voice evacuation system for complete facility has been proposed. b. Directional Sounders will be provided to guide occupants to nearest exit in case of emergency. c. Addressable fire alarm system with digital voice evacuation system is proposed which monitors and generates alarm in case of any advent of fire or smoke. d. Manual Call Points with push buttons shall be installed in the lobbies under a breakable glass enclosure painted red with control module. e. Repeater fire alarm panels have been proposed at guard room. f. Voice evacuation system generates pre-recorded evacuation messages in advent of any emergency. g. Zone wise announcements are possible to avoid stampede.
Not Applicable
Showing 1 blocks with 42 units
Total Carpet Area
9500.39 m²
102261.25 ft²
Total Units
52
2 different types
Blocks & Floors
1
6 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
9293.00 m²
100028.92 ft²