Launch Date
Completion Date
RERA ID
29.44947
77.72846
Out of total township, 10475.33 square meter plot having 1 main gate from road which has been has been completed.
2 meter hight and 230 mm thick brick work and rcc work in column and beam. Boundary wall preparation work is under progress and will be completed after completion of construction work.
from the main entrance gate we have 80 mm thick interlocking brick/rcc road, Road work is completed approx 85 percent and will be completed after completion of building construction work.
Approx 85 percent work of Footpaths work is completed
We have constructed 2 water tank in the township to supply water which will supply water .
All sewerage water shall be go to the STP which has been constructed in the township .
Strom water shall be provided. Strom water from roads and other landscape area shall be connected to the storm water drain channel and to to the rain water. Drain work is also under progress and about 85 percent work get completed.
We have provided green area with different activities which has already been completed in the township.
Tree Plantation area is under this phases, It is part of overall township and have been completed under other phases.
we have designed and implemented the system as per electricity board and have considered centralized transformer, HT panel, LT panel, Feeder pillar for common services like external lighting, STP, pump room etc.
This area is part of other phases under the township and not situated under this phase.
All sewerage water shall go to the STP and overflow from the STP shall be connected with municipal sewerage. STP has been constructed in the township.
There is a proper garbage collection area provided for solid waste management which is situated in the township.
Flushing water demand shall be fulfill by STP treated water which is situated in the township.
We will use LED light fitting in all areas which will help to reduce electricity consumption. In pump room also all the equipment shall have energy efficient motor. And we will suggest to residents also to use energy saving equipment.
This is not part of this phases as it is part of other phases which is under progress.
This is not part of this phases
This is not part of this phases
All other miscellaneous work is under progress and will be completed once the construction work is completed.
Showing 5 blocks with 20 units
Total Carpet Area
11229.68 m²
120875.15 ft²
Total Units
456
2 different types
Blocks & Floors
5
4 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
10475.33 m²
112755.40 ft²