Launch Date
Completion Date
RERA ID
28.5878
77.3979
Plot No. GH-02, Sector 120, Noida demarcation had been done by Noida Development Authority.
Yes, Masonry Pucca and Railing Boundary Wall.
Yes, RCC Trimix Road with Kerb Stone on sides and Stone Paving in front of Towers.
Yes, Footpaths will be constructed using interlocking / Paver as per Sanctioned Plans.
Yes, Water Supply from Authority further water to be collected in under Ground Water Reservoirs and Terrace Tanks, equipped with Hydro Pneumatic Pumps with GI rings and risers.
Proper sewerage will be constructed using R.C.C / UPVC pipes as per drawings and will be treated with STP.STP treated water will be used as mentioned above and residual will be disposed of in government sewerage system.
Draining system will be constructed using R.C.C. / UPVC pipes as per drawings.
Yes, Beautiful Landscape with Civil Work with Masonry and Stone, Horticulture Work and various types of Plantation.
Sufficient No. of trees as per Sanctioned Layout will be planted in the project. Beautiful landscape with civil work with masonry and stone, horticulture work and various types of plantation , shrubs , trees are to be planted out of that 50 percent will be evergreen tree.
HT electrical supply will be made by competent authority, a sub station will be set-up in project as per drawings and LT electrical supply will be available for individual unit(s). Sufficient power back-up arrangement will be made using DG Sets. Street Lighting will be done using LT supply / power back-up.
Yes, with Banquet, Gym , Indoor Games, facilities at 27th and 28th Floor lvl.
Sewerage Treatment Plant will be installed / constructed as per approved drawings. All sewerage will be treated and treated water will be available for gardening and flushing and residual of sewerage treatment plant will be drained in government sewer system.
Yes , Solid Waste will be collected manually and disposal will be done as per norms.
Water conservation will be done by rain water harvesting system and through Sewerage Treatment Plant(STP).
Good quality and approved brand equipment will be used in sub station to minimize energy loss and Solar Energy System will be installed as per norms and approved drawings.
Diesel Pump - 1 No. 2850 lpm and 150 lpm head, Electrical Pump for Hydrant - 1 No. 2850 lpm and 150 m head, Electrical Pump for Sprinkler- 1 No. 2850 lpm and 150 m head , Jockey Pumps - 2 Nos 180 lpm and 150m head, Basement internal External hydrants sprinklers. Fire tender path shall be provided as per NBC. Fire fighting systems along with pumps and UGT of Fire tank capacity (200) KL (common) and OHT of Fire tank capacity 10 KL (each block) shall be provided as per NBC and NOC from fire Department.
Proper Water Supply and Sanitary facilities on Ground Floor of Every Tower.
Yes, Refuge area provided at Every Towers on 18th ,21st 24th Floor in addition to Main and Fire Staircase. Staircase shall be provided in Basement and all the Towers for fire / emergency exit as per NBC.
Proper security system including Security Guard ,CCTV Cameras and controlled access will be made available
No: Noida/GHP/GH-2009-(VI)/2009/4604 | Date: 10-12-2009
No: Reply of Objection Letter RG Mirage Tower L Project | Date: 19-12-2021
No: Reply Letter of RG Mirage Tower L | Date: 18-01-2022
Showing 1 blocks with 106 units
Total Carpet Area
22876.16 m²
246236.70 ft²
Total Units
184
3 different types
Blocks & Floors
1
29 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
51067.00 m²
549680.08 ft²