Launch Date
Completion Date
RERA ID
28.611048
77.453134
As per approved plan, total plot area 78021.19 sqmtr out of which 8867.893 sqmtr is utilized for Nirala Aspire Phase-II
RCC plint beam, brickwork and MS railing, as per approved plan by GNIDA vide letter no. PLG/BP-3091-S/1224 dated 20.02.2020, approved map no. BA/NA/SUB/01
Front, back and side of blocks RCC, front side pavers - As per approved plan by GNIDA vide letter no. PLG/BP-3091-S/1224 dated 20.02.2020, approved map no.BA/NA/SUB/01
Pavers will be used - as per approved plan by GNIDA vide letter no. PLG/BP-3091-s/1224 dated 20.02.2020, approved map no.BA/NA/SUB/01
As per lease deed conditions water supply provided by the Greater Noida Authority and developer will distribute internally, under phase-I of project its already operational
Will made and develop by RCC/dwc pipe line - develop as per approved plan by GNIDA vide letter no.PLG/BP-3091-S/1224 dated 20.02.2020, approved map no. BA/NA/SUB/01
Develop as per approved plan by GNIDA vide letter no. PLG/BP-3091-S/1224 dated 20.02.2020, approved map no. BA/NA/SUB/01
Planned and develop as per approved plan by GNIDA vide letter no. PLG/BP-3091-S/1224 dated 20.02.2020
planned and develop as per approved plan by GNIDA vide letter no. PLG/BP-3091-S/1224 dated 20.02.2020
Install as per approved plan by GNIDA vide letter no. PLG/BP-3091-S/1224 dated 20.02.2020, approved map no. BA/NA/SUB/01, in part Nirala Aspire Phase-I its already operational
This project (Nirala Aspire Phase-II) is a part of total project and 2 community building is approved in the project consisting of area 78021.19 sqmtr out of which 1 community building already constructed in Nirala Aspire Phase-I Rera Registration no. UPRERAPRJ4730 and 1 will be constructed in another phase which is yet to be registered with RERA. There is no community building in this project known as Nirala Aspire Phase-II
This project (Nirala Aspire Phase-II) is a part of total project and under Phase-I which is already registered under RERA registration no. UPRERAPRJ4730, treatment and disposal system of sewage and sullage water through by STP capacity of 830 KLD - its already operational and this project is to be connected with the same STP/total project
This project (Nirala Aspire Phase-II) is a part of total project and under phase-I which is already registered under RERA registration no. UPRERAPRJ4730, solid waste management and disposal system is already operation and this project is to be connected with the same
Adequate number RWH provided, as per approved plan by GNIDA vide letter no. PLG/BP-3091-S/1224 dated 20.02.2020, approved map no.BA/NA/SUB/01
NA
Fire NOC received and attached, system as per approved by UP Fire Department Deputy Director by letter no. UPFS/2020/16071/GBN/GAUTAM BUDDH NAGAR/5247/DD dated 20.01.2020
As per approved plan
As per GNIDA approved plan
NA
No: Lease Deed - Bahi No.1, Jilad No.11771, Pages-71 to 114 S.No.19841 dated 17.10.2012 | Date: 17-10-2012
No: Development Agreement Between Nirala Housing Pvt Ltd and G3 Aspire Nirala Gold LLP | Date: 26-05-2022
No: Partnership Deed - LLP Agreement of G3 Aspire Nirala Gold LLP | Date: 22-01-2022
Showing 12 blocks with 82 units
Total Carpet Area
140386.00 m²
1511100.87 ft²
Total Units
142
1 different types
Blocks & Floors
12
5 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
78021.19 m²
839812.29 ft²