Launch Date
Completion Date
RERA ID
28.311587
28.306326
Designated plot is demarcated as per the lease plan issued by the authority.
Boundary wall is construct as per the sanctioned site plan.
internal roads designed of different R.O.W as per the requirement and also given in the sanctioned site plan and also uploaded.
footpaths is provided as per the Design.
municipal water supply is used for drinking purpose and details of water supply plan is also uploaded.
sewerage system as per the design calculation waste disposal plan is also uploaded.
separate drainage line is used as per the design requirement.
landscape area is provided as per local building bye laws.
as per the Design.
Electric supply including street lightning is provided as per the layout plan and details of electricity supply plan is also uploaded.
N.A, Since it is a Foot Print / Plotted Development Project.
Disposal system of sewage and sullage water is being used for landscape and flushing purpose.
All the solid waste managed as per the biodegradible waste converted in to compost and non-biodegradible delivered to registered recyclable agencies.
N.A, Since it is a Foot Print / Plotted Development Project.
N.A, Since it is a Foot Print / Plotted Development Project.
fire system and fire safety system is installed in the project as per the National Building Codes norms.
N.A, Since it is a Foot Print / Plotted Development Project
as per the Fire NOC and also uploaded in commencement certificates.
other miscellaneous work is provided as per the layout plan including Roads, Green area Electrical works etc.
Showing 1 blocks with 5 units
Total Carpet Area
0.00 m²
0.00 ft²
Total Units
0
1 different types
Blocks & Floors
1
1 floors across all blocks
Parking
0
0 garages, 0 open
Total Area
92624.89 m²
997005.05 ft²